Anthropic leases space in $10-billion Nova Scotia data centre campus

Detailed image of illuminated server racks showcasing modern technology infrastructure.
Illustrative photo.Photo by panumas nikhomkhai on Pexels

San Francisco-based Anthropic has been revealed as a long-term leaseholder of a large data centre project in Point Tupper, NS, according to BetaKit. If confirmed in full, it would be the AI company's first data centre in Canada.

Project scope and phased timeline

Halifax-based EverWind Fuels announced plans on Friday for a $10-billion data centre project at its existing campus in Point Tupper, NS. Of that investment, more than $8 billion is earmarked to develop the campus, and $2 billion is allocated to its onshore wind energy portfolio.

The campus is planned to open with a 95-megawatt (MW) phase in late 2027, followed by a 325 MW expansion slated for 2028. At full development, the campus would provide 420 MW of compute capacity.

Anthropic's role and Canadian customers

EverWind did not initially name the project's first long-term leaseholder. Anthropic later told media that the facility will power its Claude models and help meet growing demand from customers in Canada and around the world.

Both Anthropic and EverWind have signed onto Canada's Responsible Data Centre Development Principles. The framework is voluntary and not enforceable; it offers hyperscalers and regulators guidance on weighing factors such as electricity and water use when planning data centres.

Open questions

  • Will the 2028 expansion proceed as planned?
  • How much of the campus's capacity will Anthropic lease?

Key facts

  • Halifax-based EverWind Fuels announced plans on Friday for a $10-billion data centre project at its existing Point Tupper campus in NS.
  • The investment includes more than $8 billion to develop the campus, plus $2 billion for an onshore wind energy portfolio.